Thursday, May 28, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA Reportable

Interest Rate Reduced to 9% in Arbitration Dispute: Supreme Court's Ruling

Executive Engineer (R and B) and Others vs Gokul Chandra Kanungo (Dead) Thr. His LRS.

Listen to this judgment

4 min read

Key Takeaways

• A court cannot award interest for periods of inaction by a claimant.
• Section 31(7)(a) of the Arbitration and Conciliation Act grants discretion to arbitral tribunals in determining interest rates.
• Interest awarded must be reasonable and justified with reasons by the arbitral tribunal.
• Delays in raising claims can disentitle a party from receiving interest.
• The Supreme Court can exercise its powers under Article 142 to adjust interest rates in arbitration cases.

Content

INTEREST RATE REDUCED TO 9% IN ARBITRATION DISPUTE: SUPREME COURT'S RULING

Introduction

In a landmark judgment, the Supreme Court of India addressed the issue of interest rates in arbitration awards, particularly in the context of delays caused by the claimant. The Court reduced the interest rate awarded by the arbitrator from 18% to 9%, emphasizing the need for reasonableness and justification in such awards. This ruling has significant implications for arbitration practice in India, particularly regarding the conduct of parties and the discretion of arbitral tribunals.

Case Background

The case arose from a contract awarded to Gokul Chandra Kanungo for the construction of a missing link on NH-6. The contract, awarded on December 16, 1971, was to be completed within one year. However, the work was not completed until August 30, 1977, by which time the respondent had already received a significant portion of the contract amount. Following a lengthy period of inactivity, the respondent issued a notice regarding his claim in 1989, leading to a series of legal proceedings that culminated in arbitration.

The respondent's claim was initially filed under the Arbitration Act of 1940, but after its repeal, the Arbitration and Conciliation Act of 1996 came into force. The arbitrator awarded the respondent a sum of Rs. 9,20,650 along with substantial interest, which the appellants contested in subsequent legal proceedings.

What The Lower Authorities Held

The District Judge and the High Court upheld the arbitrator's award, including the interest rate of 18% per annum. The appellants argued that the interest awarded was excessive and unjustified, particularly given the long delays in the respondent's actions. They contended that the arbitrator failed to provide adequate reasoning for the interest rate and the periods for which it was awarded.

The Court's Reasoning

The Supreme Court, while reviewing the case, highlighted several key points regarding the award of interest. It noted that the discretion granted to arbitral tribunals under Section 31(7)(a) of the 1996 Act requires them to justify their decisions regarding interest rates. The Court emphasized that the arbitrator must apply their mind to the facts of the case and provide reasons for the interest awarded.

The Court found that the respondent's prolonged inaction in raising his claim, particularly the twelve-year delay from the completion of the work to the issuance of the notice, warranted a reconsideration of the interest awarded. The Court ruled that a party cannot benefit from its own lapses, and thus, the respondent was not entitled to interest for the periods of inactivity.

The Court also referenced previous judgments that established the principle that while arbitral tribunals have the power to award interest, such awards must be reasonable and based on the circumstances of each case. The Supreme Court noted that the interest awarded at 18% was excessive, especially considering the delays and the context of the case.

Statutory Interpretation

The interpretation of Section 31(7)(a) of the Arbitration and Conciliation Act was central to the Court's decision. This provision allows arbitral tribunals to award interest at a rate they deem reasonable, but it also imposes a duty on them to provide reasons for their decisions. The Court underscored that the absence of such reasoning in the arbitrator's award was a significant flaw that warranted intervention.

CONSTITUTIONAL OR POLICY CONTEXT

The ruling also reflects the Supreme Court's broader commitment to ensuring justice in arbitration proceedings. By exercising its powers under Article 142 of the Constitution, the Court aimed to balance the interests of both parties while addressing the delays and conduct that could undermine the integrity of the arbitration process.

Why This Judgment Matters

This judgment is significant for several reasons. Firstly, it clarifies the standards for awarding interest in arbitration cases, emphasizing the need for reasonableness and justification. Secondly, it reinforces the principle that parties cannot benefit from their own delays or inaction. This ruling will likely influence future arbitration awards and the approach of arbitral tribunals in determining interest rates.

Final Outcome

The Supreme Court partly allowed the appeal, ruling that the respondent would not be entitled to interest for the periods of inactivity and reducing the interest rate to 9% per annum for the remaining periods. The Court directed the parties to submit their calculations to the Executing Court, ensuring compliance with the new interest rate.

Case Details

  • Case Title: Executive Engineer (R and B) and Others vs Gokul Chandra Kanungo (Dead) Thr. His LRS.
  • Citation: 2022 INSC 1043
  • Court: IN THE SUPREME COURT OF INDIA
  • Bench: B.R. GAVAI, J. & B.V. NAGARATHNA, J.
  • Date of Judgment: 2022-09-30

Official Documents

More Judicial Insights

View all insights →
Divorce on Irretrievable Breakdown: Supreme Court's Key Ruling

Divorce on Irretrievable Breakdown: Supreme Court's Key Ruling

Gudivada Seshagiri Rao v. Gudivada Ashalatha & Anr.

Read Full Analysis
Supreme Court of India; MANMOHAN J. and N.V. ANJARIA J

Rajesh Upadhayay v. State of Bihar & Anr.

Rajesh Upadhayay v. State of Bihar & Anr.

Read Full Analysis
Shankar Lal vs Hindustan Copper Ltd: Court Upholds Employee's Birthdate for VRS Benefits