Thursday, May 28, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA Reportable

Union of India vs Manraj Enterprises: No Pendente Lite Interest Allowed

Union of India vs Manraj Enterprises

Listen to this judgment

4 min read

Key Takeaways

• A court cannot award pendente lite interest if the contract expressly prohibits it.
• Clause 16(2) of the General Conditions of Contract bars interest on amounts payable to the contractor.
• Arbitrators are bound by the terms of the contract regarding interest awards.
• Parties cannot claim interest if the contract specifically states it is not payable.
• Judicial precedents affirm that contractual terms govern the award of interest in arbitration.

Introduction

The Supreme Court of India recently addressed the issue of whether a contractor can claim pendente lite interest on amounts due under a contract when the contract explicitly prohibits such interest. In the case of Union of India vs Manraj Enterprises, the Court ruled that the contractor is not entitled to any interest pendente lite or future interest due to the specific terms outlined in the General Conditions of Contract (GCC).

Case Background

The dispute arose from a contract between the Union of India and Manraj Enterprises concerning three work contracts. Following disagreements, both parties opted for arbitration to resolve their issues. The sole arbitrator awarded a sum of Rs. 78,81,553.08 along with pendente lite interest at 12% and future interest at 18% on the awarded amount, excluding the earnest money deposit and security deposit.

The Union of India challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that clause 16(2) of the GCC explicitly barred any interest on amounts payable under the contract. The High Court upheld the arbitrator's award, leading to the present appeal.

What The Lower Authorities Held

The learned Single Judge of the High Court dismissed the Union's appeal, affirming the arbitrator's decision to award interest. The Division Bench of the High Court also confirmed this ruling, stating that the terms of the contract did not preclude the award of interest.

The Union of India contended that the contract's terms were clear and that the arbitrator had exceeded his authority by awarding interest contrary to the agreed terms. The High Court's decision was based on its interpretation of the contract and previous judicial precedents.

The Court's Reasoning

The Supreme Court, led by Justice M.R. Shah, examined the specific wording of clause 16(2) of the GCC, which states that no interest shall be payable on the earnest money, security deposit, or amounts payable to the contractor under the contract. The Court emphasized that the parties are bound by their contractual agreement, and the arbitrator, as a creature of the contract, cannot award interest contrary to its terms.

The Court referenced previous judgments, including Union of India v. Bright Power Projects (India) (P) Ltd., which established that if a contract explicitly prohibits the award of interest, the arbitrator is bound by that prohibition. The Court also noted that the expression "amounts payable to the contractor under the contract" is broad enough to encompass all payments due under the contract, including those awarded by the arbitrator.

The Court further clarified that the principle of ejusdem generis, which might limit the interpretation of terms, was not applicable in this case. The terms in clause 16(2) were disjunctive, meaning that the prohibition on interest applied independently to earnest money, security deposits, and other amounts payable.

Statutory Interpretation

The Supreme Court's ruling hinged on the interpretation of Section 31(7)(a) of the Arbitration and Conciliation Act, which allows an arbitrator to award interest unless the parties have agreed otherwise. The Court reiterated that the contract's terms take precedence, and if those terms bar interest, the arbitrator cannot award it.

The Court also distinguished between the Arbitration Act of 1940 and the current 1996 Act, noting that the latter includes explicit provisions regarding the award of interest. This distinction was crucial in determining the applicability of previous case law to the current matter.

Why This Judgment Matters

This ruling is significant for legal practice as it reinforces the principle that contractual terms govern the award of interest in arbitration. It clarifies that parties cannot claim interest if their contract explicitly prohibits it, thereby upholding the sanctity of contractual agreements. The decision serves as a reminder for parties entering into contracts to carefully consider the implications of interest clauses and the potential limitations on claims for interest in arbitration.

Final Outcome

The Supreme Court allowed the appeal, quashing the High Court's judgment and the arbitrator's award of pendente lite and future interest. The Court held that, based on the specific bar contained in clause 16(2) of the GCC, the contractor was not entitled to any interest on the amounts due under the contract.

Case Details

  • Case Title: Union of India vs Manraj Enterprises
  • Citation: 2021 INSC 754
  • Court: IN THE SUPREME COURT OF INDIA
  • Date of Judgment: 2021-11-18

Official Documents

More Judicial Insights

View all insights →
High Court's Interim Orders Under Section 100 CPC: Supreme Court's Clarification
Can Cruelty Lead to Abetment of Suicide? Supreme Court Confirms Conviction

Can Cruelty Lead to Abetment of Suicide? Supreme Court Confirms Conviction

Gumansinh @ Lalo @ Raju vs Bhikhabhai Chauhan & Anr.

Read Full Analysis
Can a Murder Accused Inherit Property? Supreme Court Clarifies Law