Sunday, April 05, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA

Pendente Lite Interest Under Arbitration Act: Supreme Court's Clarification

Oil and Natural Gas Corporation Ltd. vs. M/s G & T Beckfield Drilling Services Pvt. Ltd.

Listen to this judgment

4 min read

Key Takeaways

• Arbitral tribunals can award pendente lite interest unless explicitly barred by contract.
• The interpretation of interest clauses in contracts is crucial for arbitral awards.
• Section 31(7) of the Arbitration and Conciliation Act allows interest unless contractually restricted.
• Post-award interest is governed by statute and not subject to party agreement.
• Disputes over interest claims must be clearly defined in arbitration agreements.

Introduction

The Supreme Court of India recently addressed the complex issue of pendente lite interest in arbitration proceedings in the case of Oil and Natural Gas Corporation Ltd. vs. M/s G & T Beckfield Drilling Services Pvt. Ltd. This judgment clarifies the circumstances under which an arbitral tribunal may award interest on amounts due during the pendency of arbitration, particularly in light of contractual provisions that may seek to limit such awards.

Case Background

The appeal arose from a judgment of the Gauhati High Court, which had upheld an arbitral award in favor of M/s G & T Beckfield Drilling Services Pvt. Ltd. The arbitral tribunal had awarded a total of $6,56,272.34 to the claimant, along with interest at the rate of 12% per annum from the date the statement of claim was affirmed. The Oil and Natural Gas Corporation (ONGC) challenged this award, arguing that the agreement's clause 18.1 prohibited the payment of interest on delayed payments, including pendente lite interest.

What The Lower Authorities Held

Initially, the District Judge set aside the arbitral award, citing two main reasons: the award was non-reasoned, violating Section 31(3) of the Arbitration and Conciliation Act, and the arbitral tribunal failed to address an objection regarding the maintainability of the arbitration proceedings. However, the High Court reversed this decision, affirming the arbitral award and allowing the appeal under Section 37 of the Arbitration and Conciliation Act.

The Court's Reasoning

The Supreme Court's analysis focused on the interpretation of clause 18.1 of the agreement, which stated that ONGC would not pay interest on delayed payments or disputed claims. The Court examined whether this clause barred the award of pendente lite interest. It noted that while the arbitral tribunal had declined to award interest from the date the cause of action arose, it had awarded interest from the date the claim was affirmed before the tribunal.

The Court emphasized that Section 31(7) of the Arbitration and Conciliation Act allows an arbitral tribunal to award interest unless the parties have agreed otherwise. It clarified that the power to award interest for the period between the cause of action and the award is subject to the agreement between the parties. If the agreement is silent on the issue of interest, the tribunal has the discretion to award it.

Statutory Interpretation

The Court highlighted the distinction between pre-reference interest, pendente lite interest, and post-award interest. It noted that while pre-reference and pendente lite interest are subject to the parties' agreement, post-award interest is governed by statute and cannot be contracted out. The Court found that clause 18.1 did not explicitly bar the award of pendente lite interest, as it only addressed delayed payments and disputed claims.

Constitutional or Policy Context

The judgment underscores the importance of clear contractual language in arbitration agreements. It reinforces the principle that parties must explicitly state their intentions regarding interest in their agreements to avoid ambiguity. The ruling also aligns with the broader policy of promoting arbitration as an effective means of dispute resolution, ensuring that parties are not unduly penalized for delays in payment when the amounts are not genuinely disputed.

Why This Judgment Matters

This ruling is significant for legal practitioners and parties involved in arbitration. It clarifies the scope of an arbitral tribunal's authority to award interest, particularly in the context of contractual limitations. The decision emphasizes the need for precise drafting of arbitration agreements, especially concerning interest provisions. Legal practitioners must ensure that their clients' agreements clearly articulate their intentions regarding interest to avoid disputes and potential challenges to arbitral awards.

Final Outcome

The Supreme Court dismissed the appeal, affirming the High Court's decision to uphold the arbitral award. The Court found no merit in ONGC's arguments against the award of pendente lite interest, thereby reinforcing the arbitral tribunal's discretion in awarding interest under the Arbitration and Conciliation Act.

Case Details

  • Case Title: Oil and Natural Gas Corporation Ltd. vs. M/s G & T Beckfield Drilling Services Pvt. Ltd.
  • Citation: 2025 INSC 1066
  • Court: IN THE SUPREME COURT OF INDIA
  • Bench: Justice Manoj Misra, Justice Pamidighantam Sri Narasimha
  • Date of Judgment: 2025-09-02

Official Documents

More Judicial Insights

View all insights →
Supreme Court of India

Arbitration Cannot Be Forced Upon A Non-Signatory In Absence Of Clear Consent Or Legal Nexus, Supreme Court Reiterates

Hindustan Petroleum Corporation Ltd. v. BCL Secure Premises Pvt. Ltd. (2025 INSC 1401)

Read Full Analysis
IN THE SUPREME COURT OF INDIA

Bail Under NDPS Act: Supreme Court Grants Relief to Reginamary Chellamani

Reginamary Chellamani vs. State Rep By Superintendent of Customs

Read Full Analysis
IN THE SUPREME COURT OF INDIA