Thursday, May 28, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA Reportable

Maharashtra's HVDC Project: Supreme Court Upholds MERC's Decision

The TATA Power Company Limited Transmission vs Maharashtra Electricity Regulatory Commission & Ors.

Listen to this judgment

5 min read

Key Takeaways

• A court cannot mandate the TBCB route for tariff determination if the project is deemed existing.
• Section 62 of the Electricity Act allows for tariff determination without competitive bidding if justified.
• The Maharashtra Electricity Regulatory Commission has discretion in choosing tariff determination methods.
• Regulatory commissions must frame guidelines for tariff determination to ensure transparency and efficiency.
• Concurrent findings of fact by regulatory bodies cannot be overturned by the Supreme Court unless substantial legal questions arise.

Introduction

The Supreme Court of India recently delivered a significant judgment regarding the licensing and tariff determination for the HVDC (High Voltage Direct Current) Kudus-Aarey project, which is crucial for enhancing Mumbai's electricity transmission infrastructure. The Court upheld the Maharashtra Electricity Regulatory Commission's (MERC) decision to grant a transmission license to the Adani Electricity Mumbai Limited (AEML) for this project, clarifying the legal framework surrounding tariff determination under the Electricity Act, 2003.

Case Background

The HVDC Kudus-Aarey project was initiated to address the growing power demands of Mumbai. The project involves establishing a 1000 MW HVDC link to enhance the reliability and efficiency of power transmission in the region. The Maharashtra State Electricity Transmission Company Limited (MSETCL) had previously proposed various transmission schemes, including the HVDC project, which faced delays and changes in technology and routing.

In March 2021, MERC granted a transmission license to AEML for the HVDC project, citing its necessity for strengthening Mumbai's transmission system. However, the Tata Power Company Limited Transmission (TPC-T) challenged this decision, arguing that the project should have been subjected to the Tariff Based Competitive Bidding (TBCB) process under Section 63 of the Electricity Act, 2003.

What The Lower Authorities Held

MERC's decision was based on the premise that the HVDC project was an existing project, thus exempting it from the TBCB route. The Commission noted that the project had been part of the five-year plans and had undergone various stages of approval and modification since its inception. The Appellate Tribunal for Electricity (APTEL) upheld MERC's ruling, stating that the project did not qualify as a new project under the Government of Maharashtra's (GoM) guidelines issued in January 2019.

The Court's Reasoning

The Supreme Court's judgment focused on several key legal principles regarding the Electricity Act, 2003, and the regulatory framework governing tariff determination. The Court emphasized that:

1. **Discretion of Regulatory Commissions**: The Court affirmed that MERC has the discretion to choose between the Section 62 (Regulated Tariff Mechanism) and Section 63 (TBCB) routes for tariff determination. The absence of a threshold limit for projects did not preclude MERC from exercising its regulatory powers.

2. **Existing vs. New Projects**: The Court concurred with MERC's classification of the HVDC project as an existing project, which was crucial in determining the applicable tariff route. The Court noted that the project had been under consideration for many years and had undergone various modifications, which did not change its fundamental nature as an existing project.

3. **Guidance from National Tariff Policy**: While the NTP 2016 mandates competitive bidding for new projects, the Court clarified that it serves as a material consideration rather than a binding directive. MERC must consider the NTP while exercising its discretion but is not strictly bound by it.

4. **Regulatory Framework**: The Court highlighted the need for regulatory commissions to frame guidelines for tariff determination to ensure transparency and efficiency in the electricity sector. It directed all state regulatory commissions to establish regulations under Section 181 of the Electricity Act within three months to facilitate effective tariff regulation.

Statutory Interpretation

The judgment involved a detailed interpretation of various provisions of the Electricity Act, 2003, particularly Sections 61, 62, and 63. The Court clarified that:

- **Section 62** allows the Appropriate Commission to determine tariffs based on its discretion, while **Section 63** mandates the adoption of tariffs determined through a transparent bidding process.

- The non-obstante clause in Section 63 does not imply that it is the dominant route for all projects; both sections provide alternative methods for tariff determination.

CONSTITUTIONAL OR POLICY CONTEXT

The judgment also touched upon the broader policy implications of the Electricity Act, emphasizing the need for a balanced approach that promotes competition while ensuring consumer interests are protected. The Court recognized the challenges faced by regulatory bodies in implementing effective tariff policies and the importance of timely decision-making in the electricity sector.

Why This Judgment Matters

This ruling is significant for several reasons:

- It clarifies the legal framework governing tariff determination in the electricity sector, particularly the interplay between different sections of the Electricity Act.

- It reinforces the discretion of regulatory commissions in choosing the appropriate tariff determination method, which is crucial for adapting to the evolving energy landscape.

- The directive for regulatory commissions to frame guidelines enhances the accountability and transparency of tariff-setting processes, ultimately benefiting consumers.

Final Outcome

The Supreme Court dismissed the appeal filed by TPC-T, upholding the MERC's decision to grant the transmission license for the HVDC Kudus-Aarey project under Section 62 of the Electricity Act. The Court's ruling emphasizes the importance of regulatory discretion and the need for a robust framework for tariff determination in the electricity sector.

Case Details

  • Case Title: The TATA Power Company Limited Transmission vs Maharashtra Electricity Regulatory Commission & Ors.
  • Citation: 2022 INSC 1222
  • Court: IN THE SUPREME COURT OF INDIA
  • Date of Judgment: 2022-11-23

Official Documents

More Judicial Insights

View all insights →
Can Accused Be Convicted for Drugs Found in Another's Room? Supreme Court Acquits

Can Accused Be Convicted for Drugs Found in Another's Room? Supreme Court Acquits

Bothilal vs The Intelligence Officer Narcotics Control Bureau

Read Full Analysis
IN THE SUPREME COURT OF INDIA

Advisory Committee on Transgender Rights Expanded by Supreme Court

JANE KAUSHIK VERSUS UNION OF INDIA & ORS.

Read Full Analysis
Transfer of Family Court Cases: Supreme Court's Directive on Mediation