Sunday, April 05, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA

Interest on Arbitral Awards: Supreme Court Clarifies Section 31(7) Application

HLV LIMITED (FORMERLY KNOWN AS HOTEL LEELAVENTURE PVT. LTD.) VERSUS PBSAMP PROJECTS PVT. LTD.

Listen to this judgment

4 min read

Key Takeaways

• Section 31(7)(a) of the Arbitration Act allows arbitral tribunals to award interest as per party agreement.
• Interest awarded by the tribunal must align with the terms agreed upon in the underlying contract.
• Compound interest or interest on interest is not permissible unless explicitly stated in the award.
• The Supreme Court emphasized party autonomy in determining interest rates and terms.
• The ruling reinforces the finality of arbitral awards and limits judicial intervention at the execution stage.

Introduction

The Supreme Court of India recently delivered a significant judgment in the case of HLV Limited (formerly known as Hotel Leelaventure Pvt. Ltd.) versus PBSAMP Projects Pvt. Ltd., addressing the critical issue of interest on arbitral awards under Section 31(7) of the Arbitration and Conciliation Act, 1996. This ruling clarifies the application of interest provisions in arbitral awards and reinforces the principle of party autonomy in arbitration agreements.

Case Background

The dispute arose from a memorandum of understanding (MoU) dated April 9, 2014, between HLV Limited and PBSAMP Projects Pvt. Ltd. regarding the sale of land in Hyderabad. The MoU stipulated that PBSAMP would pay an advance of Rs. 15.5 crores to HLV for the land. However, due to disagreements, the MoU was terminated on October 9, 2024, leading to arbitration. The arbitral tribunal awarded PBSAMP Rs. 15.5 crores with interest at 21% per annum from the date of payment until repayment.

Following the award, HLV made payments totaling Rs. 44,42,05,254.00, which it claimed satisfied the award. PBSAMP, however, sought to enforce the award, claiming entitlement to compound interest. The executing court dismissed PBSAMP's claim for compound interest, leading to an appeal in the High Court, which set aside the executing court's order and remanded the matter for reconsideration.

What The Lower Authorities Held

The executing court ruled that PBSAMP was not entitled to compound interest, stating that the award only provided for simple interest at 21% per annum. The court emphasized that it could not go beyond the terms of the arbitral award. PBSAMP challenged this decision in the High Court, which found the executing court's reasoning to be inadequate and remanded the case for further consideration.

The High Court's decision was contested by HLV in the Supreme Court, which stayed the remand order pending appeal.

The Court's Reasoning

The Supreme Court, led by Justice Ujjal Bhuyan, examined the provisions of Section 31(7) of the Arbitration and Conciliation Act, which governs the award of interest in arbitral awards. The Court noted that Section 31(7)(a) allows an arbitral tribunal to include interest in the sum awarded, provided it is reasonable and agreed upon by the parties. The Court emphasized that the discretion to award interest is subject to the parties' agreement.

The Court further clarified that Section 31(7)(b) mandates that unless the award specifies otherwise, the sum directed to be paid shall carry interest at the rate of 18% per annum from the date of the award to the date of payment. The Court highlighted that the arbitral tribunal had awarded interest based on the terms of the MoU, which specified a rate of 21% per annum until repayment.

The Supreme Court rejected PBSAMP's claim for compound interest, stating that the arbitral tribunal did not award such interest in its decision. The Court reiterated that allowing a claim for compound interest would effectively rewrite the arbitral award, which is impermissible at the execution stage. The Court emphasized that the parties had agreed upon the interest regime in the MoU, and the tribunal's role was to enforce that agreement.

Statutory Interpretation

The Court's interpretation of Section 31(7) underscores the importance of party autonomy in arbitration. The provision allows parties to determine the terms of interest, and the tribunal's discretion is limited to enforcing those terms. The Court's analysis aligns with previous judgments, including Hyder Consulting (UK) Limited v. Governor, State of Orissa, which established that arbitral tribunals do not have the authority to award interest on interest unless explicitly provided for in the award.

Constitutional or Policy Context

The ruling also reflects the broader policy objective of promoting arbitration as a preferred method of dispute resolution. By reinforcing the finality of arbitral awards and limiting judicial intervention, the Supreme Court aims to enhance the efficiency and reliability of the arbitration process in India.

Why This Judgment Matters

This judgment is significant for legal practitioners and parties engaged in arbitration as it clarifies the application of interest provisions in arbitral awards. It emphasizes the importance of clearly defined terms in arbitration agreements and the need for parties to explicitly state their intentions regarding interest. The ruling also serves as a reminder that courts will not intervene to modify or expand the terms of an arbitral award during execution, thereby upholding the integrity of the arbitration process.

Final Outcome

The Supreme Court set aside the High Court's order and restored the executing court's decision, affirming that PBSAMP was not entitled to compound interest. The Court allowed the appeal, emphasizing the need to adhere to the terms of the arbitral award and the MoU.

Case Details

  • Case Title: HLV LIMITED (FORMERLY KNOWN AS HOTEL LEELAVENTURE PVT. LTD.) VERSUS PBSAMP PROJECTS PVT. LTD.
  • Citation: 2025 INSC 1148
  • Court: IN THE SUPREME COURT OF INDIA
  • Date of Judgment: 2025-09-24

Official Documents

More Judicial Insights

View all insights →
IN THE SUPREME COURT OF INDIA
IN THE SUPREME COURT OF INDIA
Validity of Demand Notice Under Section 138: Supreme Court's Clarification

Validity of Demand Notice Under Section 138: Supreme Court's Clarification

KAVERI PLASTICS VERSUS MAHDOOM BAWA BAHRUDEEN NOORUL

Read Full Analysis