Saturday, May 02, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA Reportable

Can Solar Power Developers Claim Force Majeure for Delays? Supreme Court Confirms

Bangalore Electricity Supply Company Limited vs Hirehalli Solar Power Project LLP & Others

Listen to this judgment

4 min read

Key Takeaways

• A court cannot deny a force majeure claim merely because the party did not submit a notice if the delay was not attributable to them.
• Section 125 of the Electricity Act restricts the Supreme Court's appellate jurisdiction to substantial questions of law.
• Force majeure clauses in Power Purchase Agreements must be interpreted narrowly, focusing on the specific events listed.
• Delays caused by government approvals can qualify as force majeure if the developer acted diligently.
• Liquidated damages cannot be imposed if the delay is attributable to external factors beyond the developer's control.

Introduction

The Supreme Court of India recently addressed the applicability of the force majeure clause in Power Purchase Agreements (PPAs) in the case of Bangalore Electricity Supply Company Limited vs Hirehalli Solar Power Project LLP & Others. This ruling clarifies the conditions under which solar power developers can invoke force majeure for delays in project commissioning due to external factors, particularly delays in obtaining necessary government approvals.

Case Background

The case arose from three civil appeals concerning the commissioning of solar power projects in Karnataka. The Bangalore Electricity Supply Company Limited (BESCOM) challenged the decision of the Appellate Tribunal for Electricity (APTEL), which had upheld the invocation of the force majeure clause by the Hirehalli Solar Power Project LLP and others. The core issue was whether the delays in commissioning the solar projects were due to force majeure events as defined in the PPAs.

The facts revealed that the Karnataka government had introduced a policy to promote solar energy projects, allowing farmers to develop solar power plants. The respondents, recognized as solar power developers, entered into a PPA with BESCOM, which stipulated a Scheduled Commissioning Date (SCD) for the projects. However, delays in obtaining land use conversion and evacuation approvals led the respondents to seek an extension of the SCD, invoking the force majeure clause.

What The Lower Authorities Held

The Karnataka Electricity Regulatory Commission (KERC) initially rejected the respondents' claims for extension, attributing the delays to their own actions. KERC imposed liquidated damages and reduced the tariff payable to the respondents. However, the APTEL overturned KERC's decision, finding that the delays were largely due to external factors, including the time taken by government authorities to process approvals. APTEL ruled that the respondents had acted diligently and were entitled to the benefits of the force majeure clause.

The Court's Reasoning

The Supreme Court examined the scope of its appellate jurisdiction under Section 125 of the Electricity Act, which allows appeals only on substantial questions of law. The Court emphasized that the APTEL's findings were primarily factual, focusing on whether the delays were attributable to the respondents or external factors. The Court noted that the APTEL had correctly appreciated the evidence, including the delays caused by government processes, and concluded that the respondents were not negligent in securing the necessary approvals.

The Court reiterated that force majeure clauses must be interpreted narrowly, as established in previous rulings. It highlighted that the force majeure clause in the PPA explicitly covered delays in obtaining necessary licenses and approvals, provided that such delays were not caused by the negligence of the party invoking the clause. The Court found that the APTEL had rightly determined that the delays were not attributable to the respondents, thus entitling them to invoke the force majeure clause.

Statutory Interpretation

The Court's interpretation of Section 125 of the Electricity Act was crucial in determining the scope of its appellate jurisdiction. The Court clarified that it would only entertain appeals that raised substantial questions of law, rather than re-evaluating factual determinations made by the APTEL. This interpretation reinforces the principle that specialized regulatory bodies like the APTEL are better positioned to assess factual matters and develop sector-specific laws.

Why This Judgment Matters

This ruling is significant for solar power developers and the renewable energy sector in India. It clarifies the conditions under which force majeure can be invoked, particularly in the context of delays caused by government approvals. The decision underscores the importance of diligent action by developers in securing necessary approvals while also recognizing the challenges posed by bureaucratic processes. Furthermore, it reinforces the limited scope of the Supreme Court's appellate jurisdiction, ensuring that regulatory bodies can effectively develop and interpret laws governing the electricity sector.

Final Outcome

The Supreme Court dismissed the appeals filed by BESCOM, upholding the APTEL's decision that the delays were not attributable to the respondents and that they were entitled to the benefits of the force majeure clause. The Court also confirmed that liquidated damages could not be imposed under the circumstances, and the tariff reduction imposed by KERC was unjustified.

Case Details

  • Case Title: Bangalore Electricity Supply Company Limited vs Hirehalli Solar Power Project LLP & Others
  • Citation: 2024 INSC 631
  • Court: IN THE SUPREME COURT OF INDIA
  • Bench: Justice Pamidighantam Sri Narasimha, Justice Pankaj Mithal
  • Date of Judgment: 2024-08-27

More Judicial Insights

View all insights →
IN THE SUPREME COURT OF INDIA

Victim's Right to Appeal Under Section 372 CrPC: Supreme Court's Clarification

Khem Singh (D) Through LRs vs. State of Uttarakhand & Another

Read Full Analysis
Functional Disability Assessment Under Motor Vehicle Act: Court's Ruling

Functional Disability Assessment Under Motor Vehicle Act: Court's Ruling

Sunil Kumar Khushwaha vs. Katragadda Satyanarayana & Anr.

Read Full Analysis
IN THE SUPREME COURT OF INDIA