Thursday, May 28, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA Reportable

Can Courts Grant Interim Relief Under Section 9 of the Arbitration Act? Supreme Court Clarifies

Sepco Electric Power Construction Corporation vs Power Mech Projects Ltd.

Listen to this judgment

5 min read

Key Takeaways

• A court can grant interim relief under Section 9 of the Arbitration Act if a prima facie case is established.
• The enforcement of an arbitral award is not automatically stayed by filing an application under Section 34.
• Section 36 of the Arbitration Act allows for stay of an award only under specific conditions.
• Judicial discretion in granting stay must consider the balance of convenience and the merits of the case.
• Interim measures can be sought at any stage of arbitration proceedings, including post-award.

Introduction

The Supreme Court of India recently addressed the scope of judicial powers under the Arbitration and Conciliation Act, 1996, particularly focusing on the provisions of Sections 9 and 36. This judgment clarifies the conditions under which courts can grant interim relief and the implications for parties involved in arbitration proceedings. The case involved Sepco Electric Power Construction Corporation and Power Mech Projects Ltd., where the court examined the interplay between interim measures and the enforcement of arbitral awards.

Case Background

The appellant, Sepco Electric Power Construction Corporation, a Chinese entity, was awarded contracts for coal-based power projects in India. The respondent, Power Mech Projects Ltd., was engaged as a subcontractor. Disputes arose between the parties, leading to arbitration, which culminated in an award favoring the respondent for approximately Rs. 142 crores. Following the award, the appellant filed an application under Section 34 of the Arbitration and Conciliation Act, challenging the award, and sought a stay of its operation under Section 36.

The respondent, in turn, filed an application under Section 9 of the Arbitration Act, seeking interim measures, including security for the awarded amount. The High Court directed the appellant to deposit the awarded amount, leading to the present appeal before the Supreme Court.

What The Lower Authorities Held

The High Court, in its judgment, emphasized the need for the appellant to deposit the entire awarded amount to secure the respondent's interests. The court noted that while some previous orders had directed a deposit of 50%, the circumstances of this case warranted a full deposit. The High Court also highlighted that the appellant's application for stay under Section 36 was considered alongside the respondent's application under Section 9, which the appellant contended deprived it of its legal remedy.

The High Court's decision to club the applications was contested by the appellant, who argued that it limited their ability to appeal against the interim relief granted to the respondent. The court, however, maintained that both applications were interrelated and required consideration of common factors.

The Court's Reasoning

The Supreme Court, led by Justice Indira Banerjee, examined the legal framework surrounding Sections 9 and 36 of the Arbitration Act. The court reiterated that Section 9 empowers courts to grant interim measures to secure the amount in dispute, whether before, during, or after arbitration proceedings. The court emphasized that the applicant must demonstrate a prima facie case for the relief sought.

The court clarified that the enforcement of an arbitral award is not automatically stayed by the mere filing of an application under Section 34. Instead, a separate application for stay must be made under Section 36, which allows the court to impose conditions for such stay, including the requirement to furnish security covering the awarded amount.

The court further elaborated that the power to grant stay under Section 36 is not unfettered; it is subject to the condition that the court must be satisfied that a prima facie case exists that the award was induced by fraud or corruption. The court noted that the appellant had not provided sufficient grounds to challenge the award, and the claim of it being against public policy lacked particulars.

Statutory Interpretation

The Supreme Court's interpretation of Sections 9 and 36 of the Arbitration Act is significant. Section 9 allows for a wide range of interim measures, and the court's discretion in granting such measures must be exercised judiciously. The court highlighted that while the principles of civil procedure should guide the exercise of discretion, the court is not strictly bound by them. This flexibility is crucial in ensuring that the efficacy of arbitration as a dispute resolution mechanism is upheld.

The court also underscored that the provisions of Section 36 must be read in conjunction with the Code of Civil Procedure, particularly regarding the conditions for granting stay of enforcement of an arbitral award. The court's interpretation reinforces the need for a balanced approach, weighing the interests of both parties while ensuring that the arbitration process is not undermined.

Why This Judgment Matters

This judgment is pivotal for legal practitioners and parties involved in arbitration. It clarifies the conditions under which courts can grant interim relief and emphasizes the importance of establishing a prima facie case. The ruling also delineates the procedural requirements for staying an arbitral award, ensuring that parties are aware of their rights and obligations under the Arbitration Act.

The decision reinforces the principle that the enforcement of arbitral awards should not be hindered without substantial grounds. It serves as a reminder that while parties may seek to challenge awards, they must do so with adequate justification, particularly when seeking interim measures.

Final Outcome

The Supreme Court dismissed the appeals filed by the appellant, affirming the High Court's orders regarding the deposit of the awarded amount. The court requested the High Court to expedite the pending applications under Section 34 for setting aside the award, ensuring that the matter is resolved promptly.

Case Details

  • Case Title: Sepco Electric Power Construction Corporation vs Power Mech Projects Ltd.
  • Citation: 2022 INSC 981
  • Court: IN THE SUPREME COURT OF INDIA
  • Date of Judgment: 2022-09-19

Official Documents

More Judicial Insights

View all insights →
IN THE SUPREME COURT OF INDIA

Compensation Calculation Under M.V. Act: Supreme Court's Clarification

Manorma Sinha & Anr. vs. The Divisional Manager, Oriental Insurance Company Limited & Anr.

Read Full Analysis
Evidentiary Standards for Extra-Judicial Confessions in IPC Section 302 Cases
IN THE SUPREME COURT OF INDIA

Supreme Court mandates comprehensive measures to address stray dog menace

Suo Moto Writ Petition (Civil) No. 5 of 2025

Read Full Analysis