Sunday, May 17, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA Reportable

Can Claims Arising from Arbitral Awards Be Submitted Late in CIRP? No, Says Supreme Court

M/s. RPS Infrastructure Ltd. vs Mukul Kumar & Anr.

Listen to this judgment

5 min read

Key Takeaways

• A court cannot allow claims arising from arbitral awards to be submitted after the resolution plan has been approved.
• Section 15 of the IBC mandates public announcements for CIRP, creating deemed knowledge for creditors.
• Claims must be filed within the stipulated time frame to ensure the efficiency of the CIRP process.
• Commercial entities are expected to be vigilant regarding the financial status of their debtors during insolvency proceedings.
• The principle established in Essar Steel applies, preventing the introduction of undecided claims post-approval of a resolution plan.

Introduction

The Supreme Court of India recently addressed the issue of whether claims arising from arbitral awards can be submitted after the approval of a resolution plan in the context of the Corporate Insolvency Resolution Process (CIRP). In the case of M/s. RPS Infrastructure Ltd. vs Mukul Kumar & Anr., the Court ruled against allowing belated claims, emphasizing the importance of adhering to timelines in insolvency proceedings.

Case Background

The dispute arose from an agreement dated August 2, 2006, between M/s. RPS Infrastructure Ltd. (the appellant) and M/s. KST Infrastructure Private Limited (the Corporate Debtor). The appellant alleged misconduct by the Corporate Debtor in advertising a project without acknowledging the appellant's involvement, leading to arbitration proceedings initiated on May 2, 2011. An arbitral award was issued in favor of the appellant on August 1, 2016, which included a monetary claim and directed the Corporate Debtor to transfer necessary licenses.

The Corporate Debtor challenged the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, while the appellant initiated execution proceedings. These proceedings were adjourned due to the pendency of the challenge. Subsequently, the Corporate Debtor entered CIRP initiated by homebuyers on March 27, 2019. An Interim Resolution Professional (IRP) was appointed, and a public announcement was made inviting claims from creditors.

The appellant submitted a claim of over Rs. 35 crores arising from the arbitral award but was rejected by the IRP on the grounds of late submission, as it was filed 287 days after the deadline. The appellant argued that the claim should be considered as it was contingent on the outcome of the pending appeal against the arbitral award.

What The Lower Authorities Held

The Adjudicating Authority initially granted relief to the appellant, stating that the IRP had a duty to verify the Corporate Debtor's financial records and consider the claim. However, the National Company Law Appellate Tribunal (NCLAT) overturned this decision, emphasizing the importance of adhering to timelines in the CIRP process. The NCLAT cited the Essar Steel judgment, which cautioned against allowing undecided claims after a resolution plan has been accepted, arguing that it would disrupt the resolution process.

The NCLAT's reasoning included the following points:

1. Proper service for inviting claims was effectuated by the IRP, adhering to the IBBI Regulations.

2. The appellant failed to demonstrate timely filing of the claim upon learning of the CIRP initiation.

3. The IRP made sincere efforts to collate claims, including seeking records from the Corporate Debtor's ex-management.

4. Allowing belated claims would jeopardize the approved resolution plan.

The Court's Reasoning

The Supreme Court examined the submissions from both parties, focusing on whether the appellant's claim could be included at a belated stage after the resolution plan had been approved. The Court noted that the IRP had followed the correct procedure in inviting claims and had made efforts to procure the necessary records from the Corporate Debtor. The Court emphasized that the appellant, being a commercial entity, should have been vigilant regarding the Corporate Debtor's insolvency status.

The Court highlighted that the IBC is a time-bound process, and while there are circumstances under which timelines can be extended, the appellant's delay of 287 days was excessive. The Court ruled that the appellant had deemed knowledge of the CIRP due to the public announcement mandated by Section 15 of the IBC, and their claim could not be entertained at this late stage.

Statutory Interpretation

The Court's ruling underscored the importance of adhering to the timelines set forth in the IBC and the IBBI Regulations. Section 15 mandates public announcements for CIRP, which serve to inform creditors of the insolvency proceedings and create deemed knowledge. This statutory framework is designed to ensure the efficiency and effectiveness of the insolvency resolution process, preventing delays and uncertainties that could arise from belated claims.

Constitutional or Policy Context

The judgment aligns with the broader policy objectives of the IBC, which aims to provide a time-bound and efficient mechanism for resolving insolvency. By disallowing late claims, the Court reinforced the principle that all creditors must act promptly to protect their interests and that the resolution process should not be prolonged by the introduction of new claims after a resolution plan has been approved.

Why This Judgment Matters

This ruling is significant for legal practice as it clarifies the treatment of claims arising from arbitral awards within the context of the IBC. It establishes that creditors must be proactive in filing claims within the stipulated time frames to avoid being barred from participating in the resolution process. The decision also emphasizes the need for commercial entities to remain vigilant regarding the financial status of their debtors, particularly when insolvency proceedings are initiated.

Final Outcome

The Supreme Court dismissed the appeal, affirming the NCLAT's decision and leaving the parties to bear their own costs. The ruling serves as a reminder of the importance of adhering to timelines in insolvency proceedings and the consequences of failing to do so.

Case Details

  • Case Title: M/s. RPS Infrastructure Ltd. vs Mukul Kumar & Anr.
  • Citation: 2023 INSC 816 (Reportable)
  • Court: IN THE SUPREME COURT OF INDIA
  • Bench: Justice Sanjay Kishan Kaul, Justice Sudhanshu Dhulia
  • Date of Judgment: 2023-09-11

More Judicial Insights

View all insights →
Intra-State Prison Transfer Under Section 29: Supreme Court's Ruling

Intra-State Prison Transfer Under Section 29: Supreme Court's Ruling

The State of Jharkhand & Others vs. Vikash Tiwary @ Bikash Tiwary @ Bikash Nath

Read Full Analysis
Mohd. Jamil vs State of Haryana: Conviction Under Section 302 IPC Set Aside
Manish Sisodia's Bail Plea Denied: Supreme Court Addresses Money Laundering Charges