Monday, June 01, 2026
info@thelawobserver.in
IN THE SUPREME COURT OF INDIA Reportable

Can Arbitrators Award Interest Despite Contractual Prohibitions? Supreme Court Clarifies

Jaiprakash Associates Ltd. (JAL) vs Tehri Hydro Development Corporation India Ltd. (THDC)

Listen to this judgment

5 min read

Key Takeaways

• A court cannot allow arbitrators to award interest if the contract explicitly prohibits it.
• Clauses in contracts that bar interest must be strictly interpreted to determine their applicability.
• Under the Arbitration and Conciliation Act, 1996, arbitrators cannot award interest if the agreement expressly forbids it.
• Judicial precedents under the 1940 Act do not apply to cases governed by the 1996 Act regarding interest awards.
• Disputes over interest awards in arbitration can hinge on the specific wording of the contract clauses.

Introduction

The Supreme Court of India recently addressed a pivotal issue regarding the authority of arbitrators to award interest in the case of Jaiprakash Associates Ltd. (JAL) vs Tehri Hydro Development Corporation India Ltd. (THDC). The court's ruling clarified that if a contract explicitly prohibits the award of interest, arbitrators do not possess the jurisdiction to grant such interest, even if the parties have referred the matter to arbitration. This decision underscores the importance of precise contractual language and the implications of the Arbitration and Conciliation Act, 1996 on arbitration proceedings.

Case Background

The dispute arose from a contract awarded to Jaiprakash Associates Ltd. for executing certain works, with the agreement signed on December 18, 1998. Following the emergence of disputes, the parties referred two claims to arbitration under the Arbitration and Conciliation Act, 1996. The arbitral tribunal, comprising three arbitrators, issued a majority award on October 10, 2010, which allowed the claims to a certain extent and granted interest at a rate of 10% per annum from the date of arbitration invocation until 60 days after the award, along with future interest at 18% per annum until payment.

However, the High Court of Delhi quashed the award concerning the interest granted, citing Clauses 50 and 51 of the General Conditions of Contract (GCC), which explicitly barred the payment of interest. The appellant's intra-court appeal was dismissed, leading to the present appeal before the Supreme Court.

What The Lower Authorities Held

The High Court interpreted Clauses 50 and 51 of the GCC as categorically prohibiting the payment of interest to the contractor. Clause 50 stated that no omission by the Engineer in charge to pay the amount due would void the contract, nor would the contractor be entitled to interest on any payments in arrears. Clause 51 further reinforced this by stating that no claim for interest or damages would be entertained regarding any amounts due to disputes or delays.

The High Court concluded that the arbitrators lacked jurisdiction to award interest due to these explicit prohibitions in the contract. The court's interpretation aligned with its previous ruling in a similar case involving the same parties, reinforcing the notion that the clauses in question were designed to prevent the award of interest.

The Court's Reasoning

The Supreme Court, while deliberating on the matter, emphasized the importance of the contractual language and the implications of the Arbitration and Conciliation Act, 1996. The court noted that the arbitrators had recognized the prohibitory nature of Clauses 50 and 51 but still awarded interest based on a previous judgment regarding the powers of arbitrators under the 1940 Act. The Supreme Court clarified that the legal position had evolved with the enactment of the 1996 Act, which introduced stricter guidelines regarding interest awards.

The court reiterated that if the agreement explicitly prohibits the grant of interest, the arbitrators cannot award it. This principle was supported by various precedents, including the case of Sayeed Ahmed and Company, which distinguished the provisions of the 1940 Act from those of the 1996 Act. The court highlighted that the 1996 Act sanctifies agreements between parties, meaning that if an agreement states otherwise, no interest becomes payable from the date of the cause of action until the award is delivered.

Statutory Interpretation

The Supreme Court's ruling involved a critical interpretation of the Arbitration and Conciliation Act, 1996, particularly Section 31(7)(a), which governs the award of interest. The court noted that the 1996 Act represents a significant departure from the 1940 Act, particularly regarding the authority of arbitrators to award interest when the contract contains an express prohibition. The court's interpretation emphasized that the arbitrators must act in accordance with the general law and the specific terms of the agreement, which in this case barred the award of interest.

Constitutional or Policy Context

While the judgment did not delve deeply into constitutional issues, it highlighted the policy shift in arbitration law with the introduction of the 1996 Act. The court's ruling reflects a broader trend towards ensuring that arbitration remains a fair and predictable process, with parties bound by the terms of their agreements. This approach aims to uphold the sanctity of contracts and prevent arbitrary awards by arbitrators that contradict explicit contractual provisions.

Why This Judgment Matters

This ruling is significant for legal practice as it clarifies the limits of arbitrators' powers concerning interest awards. Legal practitioners must ensure that contracts are drafted with precise language regarding interest provisions to avoid disputes in arbitration. The decision reinforces the principle that arbitrators are bound by the terms of the agreement and cannot exceed their jurisdiction by awarding interest when explicitly prohibited. This case serves as a reminder for parties entering into contracts to carefully consider the implications of their terms, particularly concerning financial matters such as interest.

Final Outcome

The Supreme Court dismissed the appeal, upholding the High Court's ruling that the arbitrators lacked the jurisdiction to award interest due to the explicit prohibitions in the contract. The court's decision reinforces the importance of clear contractual language and the need for parties to understand the implications of their agreements in arbitration proceedings.

Case Details

  • Case Title: Jaiprakash Associates Ltd. (JAL) vs Tehri Hydro Development Corporation India Ltd. (THDC)
  • Citation: 2019 INSC 158
  • Court: IN THE SUPREME COURT OF INDIA
  • Bench: Justice A.K. Sikri, Justice S. Abdul Nazeer, Justice M. R. Shah
  • Date of Judgment: 2019-02-07

Official Documents

More Judicial Insights

View all insights →
Lease and Dealership Agreements: Supreme Court Clarifies Distinction

Lease and Dealership Agreements: Supreme Court Clarifies Distinction

Indian Oil Corporation Ltd. vs M/s Shree Ganesh Petroleum Rajgurunagar

Read Full Analysis
Can Income Tax Appeals Against Dissolved Companies Proceed? Supreme Court Clarifies

Can Income Tax Appeals Against Dissolved Companies Proceed? Supreme Court Clarifies

Commissioner of Income Tax, Jaipur vs M/s Gopal Shri Scrips Pvt.Ltd.

Read Full Analysis
Impact of Compromise on POCSO Cases: Supreme Court's Clarification

Impact of Compromise on POCSO Cases: Supreme Court's Clarification

Ramji Lal Bairwa & Anr. Versus State of Rajasthan & Ors.

Read Full Analysis